Project Delivery Systems for Construction defines CM at-Risk as:
a Project Delivery Method defined by the following characteristics:
- Design and Construction are separate contracts (versus Design-Build, in which the Contracts are combined)
- Criteria for final selection include factors other than just lowest total construction cost (versus Design-Bid-Build, in which total construction cost is the only criterion for final selection)